Performance budget reflects how well a government entity is meeting its goals and objectives. Which of…

Political Science · Public Administration UGC NET November 2021 Political Science
Performance budget reflects how well a government entity is meeting its goals and objectives. Which of the following are the central points of performance budgeting?
  • 1. It requires the establishment of performance levels and the collection of information
  • 2. The amount of work that is done is measured
  • 3. The quality or results of that work is measured
  • 4. This impacts how much money a department will receive in the future
A1, 2 & 3
B1, 2, 3 & 4 ✓ Correct
C2 & 3
D3 & 4
Correct answer: (B) 1, 2, 3 & 4 — All four points are central to performance budgeting, so the answer is 1, 2, 3 and 4.
Explanation
All four points are central to performance budgeting, so the answer is 1, 2, 3 and 4.
Performance budgeting links the funds given to a programme with the results expected from it.
It first requires setting performance levels and gathering the information needed to judge them.
It then measures the amount of work that a unit actually does.
It also measures the quality or results of that work, not just its volume.
Finally these measurements shape how much money the department will receive in future.
Since each step is essential to the tool, the answer is 1, 2, 3 and 4.

Want more like this? Create a free account to practise a full test, track your progress, and get spaced-repetition review.

Shared by Mcqkart · via Mcqkart.in

Discover more from Mcqkart

Subscribe to get the latest posts sent to your email.