Arrange the steps in a Project Method. Choose the correct answer from the options given below:
1.Evaluation
2.Purpose
3.Recording
4.Execution
5.Planning
A1, 2, 3, 5, 4
B2, 4, 5, 3, 1
C1, 4, 2 5, 3
D2, 5, 4, 3, 1 ✓ Correct
Correct answer: (D) 2, 5, 4, 3, 1
Explanation
The Project Method begins with Purpose (2), where the goal or aim of the project is set.
Next comes Planning (5), in which the steps, materials and division of work are decided.
Execution (4) follows, where learners actually carry out the planned activity.
Recording (3) keeps a continuous account of what is done throughout the project.
Evaluation (1) comes last, judging how far the purpose was achieved.
The Project Method was developed by William H. Kilpatrick on the pragmatist philosophy of John Dewey.