It takes 10 men to finish a work in 2 days. Four (4) men started to…

Paper 1 · Mathematical Reasoning and Aptitude UGC NET December 2023 (08.12.2023) Shift-II
It takes 10 men to finish a work in 2 days. Four (4) men started to execute the work, but after one (1) day, 3 of them left. How many days will it take the lone man to finish the remaining work?
A12 days
B14 days
C15 days
D16 days ✓ Correct
Correct answer: (D) 16 days — The lone man will take 16 days, so that is the answer.
Explanation
The lone man will take 16 days, so that is the answer.
Ten men finish the work in 2 days, so the total work is 20 man-days.
One man alone would take 20 days to do it all.
In the first day, 4 men together do 4 man-days, which is one fifth of the work.
So four fifths of the work remains, equal to 16 man-days.
The lone man does 1 man-day per day, so he needs 16 days for the rest.

Want more like this? Create a free account to practise a full test, track your progress, and get spaced-repetition review.

Shared by Mcqkart · via Mcqkart.in

Discover more from Mcqkart

Subscribe to get the latest posts sent to your email.