McqkartGet appPractise

Twelve men are assigned a job to be finished in 30 days. After 10 days it is observed that only one-sixth of the job is completed. How many extra men are required to complete the rest of the job within the scheduled time?

A20
B22
C18 ✓ Correct
D16
Correct answer: (C) 18
Explanation

30 men are needed in all, so 18 more must join.

12 men in 10 days did 1/6, i.e. 12 x 10 = 120 man-days for 1/6.

Whole job = 120 x 6 = 720 man-days.

Remaining 5/6 = 600 man-days, to be done in 20 days.

Men required = 600 / 20 = 30, extra = 30 - 12 = 18.

Want more like this? Create a free account to practise a full test, track your progress, and get spaced-repetition review.

Practise on Mcqkart →🎓 Book an expert →