Twelve men are assigned a job to be finished in 30 days. After 10 days it is observed that only one-sixth of the job is completed. How many extra men are required to complete the rest of the job within the scheduled time?
A20
B22
C18 ✓ Correct
D16
Correct answer: (C) 18
Explanation
30 men are needed in all, so 18 more must join.
12 men in 10 days did 1/6, i.e. 12 x 10 = 120 man-days for 1/6.
Whole job = 120 x 6 = 720 man-days.
Remaining 5/6 = 600 man-days, to be done in 20 days.
Men required = 600 / 20 = 30, extra = 30 - 12 = 18.